Revo Reorganizacios

Project name: | Revo Reorganizacios |
---|---|
Country: | Hungary, Nyirbator |
Capacity: | 16,26 MWp |
Project status: | Developed 2019 Construction phase November 2020 till April 2021 Grid connection April 2021 |
O&M: | Yes |
GS Ownership: | No |
CO2 savings: | 6.357.000 kg |
Power supply: | 5.191 Households per year |
You are currently viewing a placeholder content from Google Maps. To access the actual content, click the button below. Please note that doing so will share data with third-party providers.
More Information