Revo Reorganizacios

Project name: | Revo Reorganizacios |
---|---|
Country: | Hungary, Balassagyarmat |
Capacity: | 3,41 MWp |
Project status: | Developed 2019 Construction phase September 2020 till February 2021. Grid connection March 2021 |
O&M: | Yes |
GS Ownership: | No |
CO2 savings: | 1.329.000 kg |
Power supply: | 1.086 Households per year |